Use this screen to run a report that displays hours charged by Employee to the selected project for each day during the selected timesheet period.
In the Dates field, click to select the week.
Select this check box to display combined lower level project details in the grid.
Enter the project ID, or click to select it.
After you select the Project ID and set other options, click to populate the Details table.
The table below describes the columns that display for the Details table.
Column Headings |
Description |
Name |
This column displays the employee name |
Project ID |
This column displays the project number. |
Account ID |
This column displays the labor account number. |
PLC |
This column displays the project labor category. |
Status |
This column displays the status. |
Total Hours |
This column displays the total hours. |
Day/Month |
This column displays the day of the week and date of the month. |