Plug Project Review (NOP1/NOI1/AOP1/AOP2/AOP3)

Use this screen to run the Plug Project Review report within the New Business & Proposals Module. This report provides a list of all orgs under the Org selected and displays the YTD plug and amount for each period.

You must provide information for all enabled fields in order for the report to run as expected, else an error message displays.

Report Parameters

Options may vary depending on the report type selected.

Report Type

Select from the following report types:

A high percentage of Plug Project Budget means there is less of the budget quantified in either existing Project Budgets in backlog or as Non-Backlog Project Budgets which represent future work.

Fiscal Year

Click to select the Fiscal Year.

If you selected the Plug project Details, Plug project Summary, Budget Risk Summary report types, you need to select from the following cost group selection:

Cost Type

The Direct/Indirect option buttons allows you to choose to view either Direct Plug projects or Indirect Plug projects.

Budget Group

The Budget/Outlook option buttons allows you to select either the base budget or the latest updated forecasts.

FS Code

Click to select the FS Description.

Details

Select the check box whether you prefer to View Quarters or Combined levels of report information for viewing or printing.

Org ID

Click to select the Org ID.

Calculate

This button enables when you select the Plug project Calculation Review report type. Click this button to calculate project review.

Subtasks

After you select the Org ID and set other options, click Details link to display detailed plug project review information.