Budget/EACs Status (APT1)

Use this screen to review the status of budgets and EACs that have been created at various levels of a project. The report in this screen displays top level Budget/EAC status for all projects. You can filter the report by Project Manager, Contract Type, End Date, Report Type and Budget Type.

End Date

Enter the end date or click to filter the report according to project end date.

Budget Type

Select one of the following from the drop-down list:

EAC displays in the drop-down list only if an EAC exists for the project.

Report Type

Select the type of report you want to display. Choose from the following options:

Include Expired

Select this option to include expired tasks or projects.

Project

Manager

Enter the name or click to filter the report according to Project Manager.

Contract Type

Enter the type of contract or click  to filter the report according to Contract Type.

Subtasks

Click on the toolbar to populate the Budget/EAC Details table. The table will populate even if you did not select any report filter like Project Manager, Contract Type or End Date.

The table below describes the columns that display for all levels of detail.

Column Headings

Description

Project

This column displays the Project ID.

Bud/EAC

This column displays the budget type if Budget or EAC.

VER

This column displays the version number.

Project Title

This column displays the title of the project.

Project Manager

This column displays the name of the Project Manager.

Contract Type

This column displays the contract type.

Status

This column displays the status example: No Budget

Modifier

This column displays the name of the user who did the most recent change

Last Modified

This column displays the date of the most recent change

Approver

This column displays the name of the approver

Approval Date

This column displays the approval date

Contract Start

This column displays the contract start date

Contract End

This column displays the contract end date

PDS Remaining

This column displays the number of remaining periods left

Funding

This column displays the Funding amount

Unplanned

This column displays the Unplanned amount

Planned

This column displays the Planned amount

Click the execute button every time you change a filter to refresh the grid with the latest data.