Use this screen to display labor hours charged or budgeted to the project, or variances of labor hours charged or budgeted to the project, for the last seven accounting periods, or if you are viewing future budgets, the next seven accounting periods.
Depending on the selected report type, the following report parameters display:
Select the type of report you want to display. Choose from the following options:
Cost - Select this option to display labor hours charged to the selected project for the last seven accounting periods.
Budget - Select this option to display labor hours budgeted to the selected project for the last seven accounting periods, or if you are viewing future budgets, for the next seven periods.
Variance - Select this option to display variances of labor hours charged or budgeted to the selected project for the last seven accounting periods. Negative variances display in favor of either actuals or budgets, depending on how Report Variances in Favor of is configured on the Display tab of Planning » Administration »Administration Controls » Configuration Settings (MAM10). If configured in favor of Actuals and actual costs are higher than budgeted costs, the variance displays as negative. The opposite is true if budgeted costs are higher than actual costs, and the variance displays as positive. However, for either Budgets or Actuals, profit and revenue variances are always opposite to the cost calculation.
Select this check box to display combined hours breakdown details.
Select this check box to display all period details.
Depending on the selected report type, the following report parameters display:
If you selected the Budget or Variance report type, select one of the following from the drop-down list:
Budget - Select this option to display the latest budget information.
EAC - Select this option to display the latest EAC information.
Under Timing, select one of the following timing options:
Past - Select Past to display seven accounting periods in the past.
Future - Select Future to display seven accounting periods in the future.
Enter, or click , to select, the project ID.
To display lower level details, choose from the following links:
Hours Breakdown - Click this link to display hours breakdown details.
All Periods - Click this link if you want the report to include all periods details.