Within the Budget by Resource, use this tab to reschedule the assignment dates of the resource.
To reschedule assignment dates:
Go to Planning » Resource Planning » Budget by Resource and enter the assignment dates.
Search for the resource who currently has hours budgeted that will now be rescheduled.
Highlight the resource in the result set and click the Add/Edit/Delete Assignments subtask.
From the Add/Edit/Delete Assignments grid, select the assignment to be rescheduled and click the Action hyperlink from the Reschedule Reassign column.
The Assignment Actions group box displays. Select the Reschedule tab.
Enter the new start date in the Reschedule Start Date field. You can only edit the Reschedule Start Date. Costpoint Planning calculates the Reschedule End Date by using the same period of time in the original assignment dates. If you move the start date a year forward, the end date will also move forward a year.
Click Reschedule to change the assignment dates.