Task inquiry
unavailable in ajeraCore
A task is work that needs to be performed. You add tasks to your schedule on the Manage tab in the Project Command Center, and use them to track the progress and scope of the project.
Use this inquiry to see information for each of your tasks, such as project or phase ID and description, task description, employee or employee type, units/hours, priority, and actual start date.
If needed, you can add predefined columns and view supplemental information such as
cost amount, fee amount, and estimated start and completion dates.
Using the inquiry
From the Inquiry menu, click Resource > Task.
Audience
Accounting staff
Groups
This inquiry is grouped by Project ID & Description and Phase ID & Description. You can always
group or ungroup
columns, as needed.
Standard columns
Project ID & Description
|
Project
|
The ID and description of the project associated with the task
|
|
Phase ID & Description
|
Phase
|
The ID and description of the phase associated with the task
|
|
Resource/Task Description
|
|
The name of the task
|
|
Employee
|
Employee
|
The name of the employee assigned to the task
|
|
Employee Type
|
Employee Type
|
The name of the employee type assigned to the task
|
|
Activity
|
Activity
|
The name of the activity assigned to the task
|
|
Vendor
|
Vendor
|
The name of the vendor assigned to the task
|
|
Reference/Commitment #
|
|
A short description that further identifies the task
|
|
Units/Hours
|
|
The number of units or hours assigned to the task
|
|
Status
|
|
The status of the task, which is selected on the Manage tab of the Project Command Center
Examples: In Progress, Not Started, Complete, Waiting, Deferred
|
|
Priority
|
|
The importance of the task
Examples: High, Medium, Low
|
|
Actual Start Date
|
|
The actual date when work begins
|
|
Notes
|
|
Any notes about the task
|
|
RPC
|
Reported % Complete
|
The percentage entered in the % Complete column for the task on the Manage tab of the Project Command Center
|
|
Defined links:
|
RPC
|
Reported % Complete
|
A link to the Reported % Complete inquiry
|
|
Predefined columns
You can add predefined
columns to this inquiry. Many columns are available, organized in
these categories:
Project and phase:
|
Project Key
|
Project
|
The database identifier of the project associated with the task
|
|
Project ID
|
Project
|
The ID of the project associated with the task
|
|
Project Description
|
Project
|
The name of the project associated with the task
|
|
Phase Key
|
Phase
|
The database identifier of the phase associated with the task
|
|
Phase ID
|
Phase
|
The ID of the phase associated with the task
|
|
Phase Description
|
Phase
|
The name of the phase associated with the task
|
|
Phase Order
|
|
The position of the phase associated with the task in the Project Command Center
Example: You may sort the inquiry by phase order so it mirrors the order of the work breakdown structure in the Project Command Center.
|
|
Resource/task:
|
Resource Key
|
|
The database identifier of the task
|
|
Order
|
|
The position of the task on the Manage tab in the Project Command Center
Example: You may sort the inquiry by task order so it mirrors the order of the tasks on the Manage tab.
|
|
Is Task
|
|
Indicates whether this is a task
|
|
Parent Resource Key
|
|
The database identifier of the parent resource of the task
|
|
Activity, employee, and vendor:
|
Activity Key
|
Activity
|
The database identifier of the activity associated with the task
|
|
Activity Type
|
|
The activity type associated with the task
Examples: Labor, Expense, or Consultant
|
|
Employee Type Key
|
Employee Type
|
The database identifier of the employee type associated with the task
|
|
Employee Key
|
Employee
|
The database identifier of the employee associated with the task
|
|
Vendor Type Key
|
Vendor Type
|
The database identifier of the vendor type associated with the task
|
|
Vendor Type
|
Vendor Type
|
The vendor type associated with the task
|
|
Vendor Key
|
Vendor
|
The database identifier of the vendor associated with the task
|
|
Amounts and rates:
|
Cost Rate
|
|
The rate that reflects the actual cost of the task without overhead or profit
|
|
Cost Amount
|
|
The amount paid to employees for work performed, or the out-of-pocket costs to the company for expenses and consultants, for the task
|
|
Fee Rate
|
|
For billable billing types, the billing rate for the task
|
|
Fee Amount
|
|
For billable billing types, the contract amount of the task
|
|
Markup Rate
|
|
|
|
Beginning Balance Cost Amount
|
|
The amount entered in the Committed Cost Invoiced column on the Manage tab of the Project Command Center for the expense or consultant task
|
|
Beginning Balance Fee Amount
|
|
The amount entered in the Committed Contract Invoiced column on the Manage tab of the Project Command Center for the expense or consultant task
|
|
Dates:
|
Reported % Complete Date
|
Reported % Complete
|
The date when you report the percent of work that is complete for the task
|
|
Estimated Start Date
|
|
The date when work is scheduled to begin for the task
|
x
|
Estimated Completion Date
|
|
The date when work is scheduled to be complete for the task
|
x
|
Actual Completion Date
|
|
The actual date when work is complete for the task
|
x
|
Miscellaneous:
|
Percent Distribution
|
|
The percent of the total hours/units, cost amount, or contract amount represented by the task
|
|
See also
About key fields
About standard inquiries
Adding a predefined
inquiry column
Creating a new inquiry column
Displaying
inquiry data for a specific time period
|
|